The Welshpool & Llanfair Light Railway

THE PERMANENT WAY 

"2002/2003 track work"

Llanfair Station

Track work this winter started with the Autumn track week commencing with the laying of a "NEW" crossover for Llanfair station. New 50lb rail, fixings and sleepers shown after completion of the job.

Llanfair Station New Crossover

Dirty Lane to Dolarddyn

 The Spring 2003 track work was concentrated near "Dirty Lane" (MP 6/0 to 5/II) to Dolarddyn Straight. Lifting old 45lb rail and mainly heavy ex London Transport hard wood sleepers. These were replaced with new (South African) 60lb (30kg/m) rails and the last of the Australian Karri hard wood sleepers and the new hard wood's from Brazil's sustainable forests. Fitting of rails was by MOD (Ministry of Defense) Clips and screws which have been found to be more secure than the base plate and spike's used before."MOD" Clip and screw fixing

Between Dirty Lane and High GirdersDirty Lane crossing and track gangers given a JCB lift

SYLFAEN

Work continued to replace the main line through Sylfaen Station which was lifted last year when the 56lb ex Tanat Valley rail was moved over the Sylfaen summit, near MP 3/I, to extend the 56lb lengths which now run from Sylfaen (Wlp end points) over the summit by a further 10 lengths.

Relaying Sylfaen Station Platform RoadSylfaen Station Relaying the Platform Road

All in all a busy 2002/03 winter on the track.